As this project continues to evolve, we’re committed to bringing you the latest information about the construction process and continued progress. Please visit us online at CookCountyLCR.org to view weekly construction updates shared by the project team. |
|
|
TRAVEL ADVISORY: A new traffic pattern along Lake Cook Road between the Target and Walmart and Hastings Lane is starting today, November 20, 2020. A new traffic pattern along Lake Cook Road between Raupp Boulevard and the Target and Walmart is starting the week of November 23, 2020. Traffic will be opened up to two lanes in each direction with left-turn lanes for the upcoming winter shutdown. Be alert when driving through the new traffic configuration in the work zone. |
|
|
Monday, November 9, 2020 R.W. Dunteman Company paved along eastbound Lake Cook Road lane 3 from Buffalo Grove Road to the Walmart and Target entrances, prepared for various hand pours throughout the job site by setting, forming, and placing dowel bar baskets…Read more |
|
|
Tuesday, November 10, 2020 Areatha continued to frame the Buffalo Grove Road Bridge deck and worked on excavating for the Buffalo Grove Road Bridge northeast wing wall… Read more |
|
|
Wednesday, November 11, 2020 Trine removed the existing water main and storm sewer system to install the proposed storm sewer pipes and structures at the northeast corner of Lake Cook Road and Buffalo Grove Road…Read more |
|
|
Thursday, November 12, 2020 R.W. Dunteman Company continued to pour temporary pavement on IL-83 north and south of Lake Cook Road, prepared subgrade at the northwest corner of Lake Cook Road and Lexington Drive, and excavated for the sleeper slab placement at the Lake Cook Road and Weiland Road intersection…Read more |
|
|
Friday, November 13, 2020 Areatha continued to frame the Buffalo Grove Road Bridge diaphragms and set rails on beams for the upcoming bridge deck pour…Read more |
|
|
Saturday, November 14, 2020 Areatha continued to set front face forms on the northeast wing wall on Buffalo Grove Road Bridge...Read more |
|
|
Stay up to date on this project! To learn more about the Cook County Lake Cook Road Reconstruction Project, visit the project website at CookCountyLCR.org. If you have any additional questions, please send us an email at info@CookCounyLCR.org or contact the message center at (847) 497-0860. Please help us spread the word about the project and encourage your neighbors to subscribe to email communications by clicking the "Learn More" button below. |
|
|