Thank you for your continued interest in the Cook County Lake Cook Road Reconstruction Project! Our team is committed to bringing you the latest information about the construction process and continued progress. If you have any questions or comments, please send an email to info@CookCountyLCR.org. |
|
|
TRAVEL ADVISORY Lake Cook Road from Raupp Boulevard to Hasting Lane is currently open to one lane in each direction with dedicated left turn lanes at each intersection. Daily lane shifts are expected to complete work at each intersection. Expect delays and be alert when traveling through the work zone. Final pavement markings will be placed early next week, and traffic will shift to the final configuration on Lake Cook Road, Buffalo Grove Road, IL-82, and Weiland Road on November 24, 2021. |
|
|
Monday, November 8, 2021 Areatha poured the connector pavement on the south side of the Buffalo Grove Road Bridge...Read more |
|
|
Tuesday, November 9, 2021 Home Towne installed light pole bases along eastbound Lake Cook Road, drilled and poured light pole foundations along northbound Weiland Road north of Lake Cook Road...Read more |
|
|
Wednesday, November 10, 2021 R.W. Dunteman Company prepared and poured pavement on southbound Buffalo Grove Road south of the Buffalo Grove Road Bridge, placed asphalt surface on Weiland Road and St Mary’s Parkway...Read more |
|
|
Thursday, November 11, 2021 Areatha framed the sidewalk approaches and bridge deck of the Buffalo Grove Road Bridge...Read more |
|
|
Friday, November 12, 2021 Areatha framed the sidewalk approaches and bridge deck of the Buffalo Grove Road Bridge...Read more |
|
|
Saturday, November 13, 2021 R.W. Dunteman Company broke the existing and temporary pavement along southbound Buffalo Grove Road north of Lake Cook Road, framed for the new sidewalk along westbound Lake Cook Road between IL-83 and Raupp Boulevard...Read more |
|
|
Stay up to date on this project! To learn more about the Cook County Lake Cook Road Reconstruction Project, visit the project website at CookCountyLCR.org. If you have any additional questions, please send us an email at info@CookCounyLCR.org or contact the message center at (847) 497-0860. Please help us spread the word about the project and encourage your neighbors to subscribe to email communications by clicking the "Learn More" button below. |
|
|