Weekly Construction Update

Thank you for your continued interest in the Cook County Lake Cook Road Reconstruction Project! Our team is committed to bringing you the latest information about the construction process and continued progress. If you have any questions or comments, please send an email to info@CookCountyLCR.org.

TRAVEL ADVISORY

Lake Cook Road from Raupp Boulevard to Hasting Lane is currently open to one lane in each direction with dedicated left turn lanes at each intersection. Daily lane shifts are expected in the next couple of weeks to complete work at each intersection. Be alert when traveling through the work zone and expect delays.

Monday, October 18, 2021 

Quality Saw prepared longitudinal pavement joints along eastbound and westbound Lake Cook Road and placed sealant in joints...Read more

Tuesday, October 19, 2021 

R.W. Dunteman Company prepared and poured concrete pavement for southbound and northbound Buffalo Grove Road left turn lanes at the Weiland Road intersection...Read more

Wednesday, October 20, 2021 

Home Towne drilled light pole foundations along southbound IL-83 south of Lake Cook Road and installed conduit and traffic signal handholes at the IL-83 and Weiland Road intersection...Read more

Thursday, October 21, 2021 

R.W. Dunteman Company poured concrete curb and gutter, and sidewalk along northbound Weiland north of Lake Cook Road, poured pavement segments at the IL-83 and Weiland Road intersections on Lake Cook Road...Read more

Friday, October 22, 2021 

R.W. Dunteman Company poured concrete curb and gutter, and sidewalk along northbound Weiland north of Lake Cook Road, poured pavement segments at the IL-83 and Weiland Road intersections on Lake Cook Road...Read more

Saturday, October 23, 2021 

Areatha placed bidwell on Buffalo Grove Road Bridge deck...Read more

Stay up to date on this project!

To learn more about the Cook County Lake Cook Road Reconstruction Project, visit the project website at CookCountyLCR.org. If you have any additional questions, please send us an email at info@CookCounyLCR.org or contact the message center at (847) 497-0860.

 

Please help us spread the word about the project and encourage your neighbors to subscribe to email communications by clicking the "Learn More" button below. 

Learn More

Media Inquiries

All media inquiries regarding the Cook County Lake Cook Road Reconstruction Project should be directed to Natalia Derevyanny at natalia.derevyanny@cookcountyil.gov

or Brittany Hill at brittany.hill@cookcountyil.gov.