Thank you for your continued interest in the Cook County Lake Cook Road Reconstruction Project! Our team is committed to bringing you the latest information about the construction process and continued progress. If you have any questions or comments, please send an email to info@CookCountyLCR.org. |
|
|
TRAVEL ADVISORY Lake Cook Road has been reduced to one lane eastbound from Raupp Boulevard to Hastings Lane. Starting May 14, 2021, westbound Lake Cook Road from Hastings Lane to Raupp Boulevard will be reduced to one lane. Expect delays and be alert when driving through the work zone. |
|
|
Monday, May 3, 2021 Areatha continued the removal of the existing parapet wall on the west side Buffalo Grove Road Bridge deck…Read more |
|
|
Tuesday, May 4, 2021 R.W. Dunteman poured concrete pavement, curb and gutter driveways and temporary pavement on southbound Weiland Road south of Lake Cook Road…Read more |
|
|
Wednesday, May 5, 2021 R.W. Dunteman continued to excavate and prepare for subgrade on southbound Weiland Road north of Lake Cook Road…Read more |
|
|
Thursday, May 6, 2021 Trine continued the removal and replacement of the storm sewer pipe and structures along eastbound Lake Cook Road...Read more |
|
|
Friday, May 7, 2021 R.W. Dunteman continued the removal of existing pavement and curb and gutter along Weiland Road...Read more |
|
|
Saturday, May 8, 2021 Areatha continued to frame the Weiland Road Bridge deck for the upcoming deck pour...Read more |
|
|
Stay up to date on this project! To learn more about the Cook County Lake Cook Road Reconstruction Project, visit the project website at CookCountyLCR.org. If you have any additional questions, please send us an email at info@CookCounyLCR.org or contact the message center at (847) 497-0860. Please help us spread the word about the project and encourage your neighbors to subscribe to email communications by clicking the "Learn More" button below. |
|
|