Weekly Construction Update

As this project continues to evolve, we’re committed to bringing you the latest information about the construction process and continued progress. Please visit us online at CookCountyLCR.org to view weekly construction updates shared by the project team.

TRAVEL ADVISORY:

Lake Cook Road is reduced down to one lane in each direction between Raupp Boulevard and Lexington Drive. Expect long delays and be alert for the new traffic pattern along Lake Cook Road.

 

Pattern Change on IL-83 (McHenry Road) began on 6/29/20. Be alert when driving through the work zone.

 

The Contractor began placing traffic into Stage 4 Maintenance of Traffic Configuration along IL-83 the week of 6/29/20. Once traffic is placed in this configuration the Contractor will be able to finish storm sewer installations and start the reconstruction of the roadway. During this stage, IL-83 (McHenry Road) will remain a single lane in each direction from Pauline Avenue to Fairview Drive. Be alert when driving through the work zone and expect long delays. Read more

Monday, June 22, 2020

R.W. Dunteman Company placing aggregate subgrade along the south leg of Buffalo Grove Road, also removing curb and gutter along eastbound Lake Cook Road near Lexington in preparation for temporary pavement... Read more

Tuesday, June 23, 2020

Home Towne continues the removal of concrete foundations from the existing traffic signals at the intersection of Lake Cook Road and the Target/Walmart entrance... Read more

Wednesday,
June 24, 2020

R.W. Dunteman Company pours temporary pavement at the southwest corner of IL-83 and Lake Cook Road and pour the pavement sleeper slab for the intersection of Buffalo Grove Road and Weiland Road... Read more

Thursday, June 25, 2020

Atlantic clean steel beams to prepare for painting by south abutment of Buffalo Grove Road bridge... Read more

Friday, June 26, 2020

Home Towne continues to break and remove concrete foundations of traffic signals and hand holes along Lake Cook Road... Read more

Saturday, June 27, 2020

Trine continues to remove existing storm sewer and install new storm sewer pipe and structures along Weiland Road between IL-83 and Lake Cook Road, also continues installation of storm sewer along westbound Lake Cook Road... Read more

Stay up to date on this project!

To learn more about the Cook County Lake Cook Road Reconstruction Project, visit the project website at CookCountyLCR.org. If you have any additional questions, please send us an email at info@CookCounyLCR.org or contact the message center at (847) 497-0860.

 

Please help us spread the word about the project and encourage your neighbors to subscribe to email communications by clicking the "Learn More" button below. 

Learn More