Work Completed in the Last Few Weeks:
Seeding and erosion control blanket along Woods Creek 95% complete.
Seeding and erosion control blanket installed around basin 3 (off of Brookside Ave).
Western construction entrance removed and site access is now off of Stonegate Rd.
Grading and stone checks installed within wetland B.
Channel Seeding Within Wetland B
Next Steps for the Woods Creek Restoration Project:
Work around wetland B will be completed.
Wetland B will be seeded and covered with erosion control blanket and straw mulch.
Stormwater repairs within Basin 1 will be completed and will include a new flared end section and rock protection around all pond inlets/outlets.
Earthwork will begin in wetland C.
Stone Check Installed Within Wetland B
Stream Treatment Information
Outlet protection refers to the use of rip rap or stone to protect the space between a stormwater outlet and the creek. Lining the space between the flared end section of the stormwater pipe and the stream provides a protected path for rainfall to travel to get to the creek. This will prevent erosion and will lengthen the life of our valuable stormwater infrastructure within the Village of Algonquin.