Weekly Construction Update

Thank you for your continued interest in the Cook County Lake Cook Road Reconstruction Project! Our team is committed to bringing you the latest information about the construction process and continued progress. If you have any questions or comments, please send an email to info@CookCountyLCR.org.

TRAVEL ADVISORY

Lake Cook Road from Raupp Boulevard to Hasting Lane is currently open to one lane in each direction with dedicated left turn lanes at each intersection. Expect delays and be alert when traveling through the work zone.

 

St Mary’s Parkway will be closed between Buffalo Grove Road and Navajo Trail. Please use the signed detour routes to access St Mary’s Parkway from Buffalo Grove Road.

Wednesday, July 14, 2021 

R.W. Dunteman Company framed and poured curb and gutter on southbound Buffalo Grove Road north of Lake Cook Road...Read more

Thursday, July 15, 2021

Areatha completed framing the north parapet wall on Weiland Road Bridge and continued to install the wall drain on retaining Wall C...Read more

Friday, July 16, 2021

Trine continued the installation of storm sewer pipe and structures along westbound Lake Cook Road east of IL-83...Read more

Stay up to date on this project!

To learn more about the Cook County Lake Cook Road Reconstruction Project, visit the project website at CookCountyLCR.org. If you have any additional questions, please send us an email at info@CookCounyLCR.org or contact the message center at (847) 497-0860.

 

Please help us spread the word about the project and encourage your neighbors to subscribe to email communications by clicking the "Learn More" button below. 

Learn More

Media Inquiries

All media inquiries regarding the Cook County Lake Cook Road Reconstruction Project should be directed to Natalia Derevyanny at natalia.derevyanny@cookcountyil.gov

or Brittany Hill at brittany.hill@cookcountyil.gov.