Dear Owners & Residents,
Below is an update from the second week of our major project for 2020, and the project continues to move forward ahead of schedule. If you missed the last news letter it can be found here
Driveway Pipe Camera Inspection and Repairs
The works are were delayed. The contractor has now indicated that these works will prevent access to the garage and so we are waiting until after the major project to establish a date. We ask that you have a heightened sense of safety for any persons located in the driveway.
Sound & Balconies
We recently had an incident where a resident had a late night party with loud music radiating and revirbarating through the building at 11:30pm.
All residents are reminded that:
- by-laws prevent any offensive activity that may be, or become, an annoyance or nuisance
- to report any late parties to both the building manager on the after hours number and police.
By-Laws
All owners and occupiers should be familiar with the By-Laws available from the Resources Page on TankTower.com.au
2020 Project Update
Week 1 recap
Follow this link if you missed the Week 1 News Letter that provides information about the following items completed during week 1:
- Driveway Pipe Shaft block work
- New hobs, waterproofing, tile bedding and additional waterproofing of Pump Room, Common Area Balcony and Doorway to Pool
- Common area ceiling height design
Week 2 progress
Below are the details of work completed during week 2.
Concrete Repairs to Level 4 & 5
Following the waterproofing work last week, preventing water from dripping through to Level 4, the team were able to remove damaged concrete on the underside of the slab and then undertake steel and concrete repairs. Specialised equipment was required to provide access to the area under the pump room to complete the repairs over two days.