Thank you for your continued interest in the Cook County Lake Cook Road Reconstruction Project! Our team is committed to bringing you the latest information about the construction process and continued progress. If you have any questions or comments, please send an email to info@CookCountyLCR.org. |
|
|
TRAVEL ADVISORY Lake Cook Road from Raupp Boulevard to Hasting Lane is currently open to one lane in each direction with dedicated left turn lanes at each intersection. Expect delays and be alert when traveling through the work zone. St Mary’s Parkway will be closed between Buffalo Grove Road and Navajo Trail until the week of June 28, 2021. Please use the signed detour routes to access St Mary’s Parkway from Buffalo Grove Road. |
|
|
Tuesday, June 1, 2021 R.W. Dunteman Company excavated and prepared subgrade on southbound Buffalo Grove Road north of Lake Cook Road…Read more |
|
|
Wednesday, June 2, 2021 Areatha poured the remaining sections of the approach slab footings on the Weiland Road Bridge and continued to drill and set soldier piles for retaining Wall C…Read more |
|
|
Thursday, June 3, 2021 Trine installed pipe underdrain on southbound IL-83 north of Lake Cook Road and removed and replaced storm sewer pipe and structures along westbound Lake Cook Road west of Buffalo Grove Road...Read more |
|
|
Friday, June 4, 2021 Trine finished the remaining work with the sanitary sewer along westbound Lake Cook Road by the Jewel shopping center...Read more |
|
|
Saturday, June 5, 2021 Areatha prepared forms for the approach slabs on the east and west side of Weiland Road bridge...Read more |
|
|
Stay up to date on this project! To learn more about the Cook County Lake Cook Road Reconstruction Project, visit the project website at CookCountyLCR.org. If you have any additional questions, please send us an email at info@CookCounyLCR.org or contact the message center at (847) 497-0860. Please help us spread the word about the project and encourage your neighbors to subscribe to email communications by clicking the "Learn More" button below. |
|
|