Next Steps
Some of the work expected this coming week, subject to weather, includes...
a) Completion of one Podium Lot
b) Installation of the tile bed and top layer of waterproofing to the second Podium Lot
c) Installation of glass barrier around the pool
d) Waterproofing to the tower rooftop
Noisy Works
There maybe infrequent periods where some noise will be experienced, but the noise will be much reduced when compared to the first few weeks of the project.
Builders hours
Approved work hours are between 8am to 5pm Monday to Friday, and 9am to 3pm Saturday.
Car Parking
The builder has been allocated several car parks during the project. The two visitors parks on Ground Floor should remain available to visitors. We remind you that visitors also have the option to park in the paid parking station at 40 Tank Street.
Driveway
The builder will occasionally require exclusive use to the driveway parking bays, so please ensure the office staff are aware of any furniture delivery or removals several days in advance.
Lift Use
One lift has been allocated to builders during the project and will have protection installed. Occupants can still use the lift allocated to builders.
Level 5 Pool & Gym
Level 5 Pool & Gym remains shut through to project completion.
Ways that you can prepare
Suggestions include:
If you have additional questions or suggestions, please submit them using the TankTower.com.au Contact page.
We appreciate your patience while this important project is undertaken.
Thanks for your patience during this work.
Phill Jones – Tank Tower Chairperson